Monday, June 10, 2024

Planned Post Goods Issue Date is the same as Delivery Date

 While creating a STO - Outbound delivery through VL10B, the Planned Delivery Date (Planned PGI date) is the same as the STO Delivery date in ME23N. 

For example, it takes 20 days to deliver to the receiving plant. It is expected that the picking/loading/goods issue should be proposed at least 20 days before the delivery date.

Issue

Create an Outbound Delivery by VL10B against a STO;

Check the Planed GI Date on Outbound, it is the same date as Delivery date on STO.

Reason

Missing configuration Settings.

Solution

Ø  Transaction code 0VLK and set "Rescheduling" as ‘X’ for delivery type involved on the flow(NLCC for example).

Example:

Blank   No rescheduling

X          Reschedule if deadlines are in the past

Y          Like X or route changed or route schedule changed

A          Reschedule after relevant changes


Transaction code OVLY, SD scheduling is not active, DlvSchelg and TranspSchd need to be ‘X’, for order type DL



No comments:

Simple explanation about SAP BRF+/BRFplus

                             SAP Business Rules Framework plus (BRF+) is a powerful tool within the SAP ecosystem for defining and managing ...