STO process in Subcontracting
We are referring to the Subcontracting Stock
Transfer Order (STO) process in the context of SAP or a similar ERP system.
Subcontracting is a business arrangement where a company sends components or
raw materials to a subcontractor (a third-party manufacturer) to have them
processed or assembled into finished goods.
Here's a general outline of the Subcontracting
Stock Transfer Order process:
Create Purchase Requisition (PR):
A purchase requisition is created to initiate
the procurement process. This is usually generated based on the requirements
for the components that need to be sent to the subcontractor.
Create Purchase Order (PO):
A purchase order is created based on the
purchase requisition. The PO specifies the details of the subcontracting
arrangement, including the components to be sent, quantities, delivery dates,
and the subcontractor's details.
Goods Issue (GI) - Stock Transfer to
Subcontractor:
Before sending the materials to the
subcontractor, a goods issue is performed to reduce the stock of the components
in the issuing plant. This is done using a stock transport order (STO) to
transfer the materials to the subcontractor's stock.
Transportation of Components to Subcontractor:
The components are physically transported to
the subcontractor's location. This may involve coordination with a logistics or
transportation system.
Goods Receipt (GR) at Subcontractor:
When the subcontractor receives the
components, they perform a goods receipt to acknowledge the receipt of the
materials into their stock.
Subcontracting Process at Subcontractor's
Facility:
The subcontractor processes or assembles the
components into finished goods according to the specifications outlined in the
purchase order.
Goods Issue (GI) - Finished Goods Transfer:
Once the subcontracting process is complete,
the subcontractor issues the finished goods back to the originating plant using
a goods issue.
Goods Receipt (GR) - Finished Goods at the
Originating Plant:
The originating plant receives the finished
goods through a goods receipt, and the stock is updated accordingly.
Invoice Verification (MIRO):
The originating plant performs invoice
verification to process the subcontractor's invoice based on the services
provided.
Payment to Subcontractor:
The payment is made to the subcontractor based
on the terms agreed upon in the purchase order.
This process ensures that the components are
sent to the subcontractor, processed into finished goods, and then returned to
the originating plant, all while maintaining proper stock and financial records
in the ERP system.