Different dates in SAP delivery and how the date calculation logic works with example
SAP delivery dates play a critical role in managing the entire shipping process, from order creation to goods issue. Here's a breakdow...
-
Account Assignment Category in SAP MM Definition Account Assignment category is one of the very important fi...
-
Source: http://www.atoziq.com 1 . Introduction to SAP MM 1. What is SAP? How is it used in industries? ...
-
Currently this Post Changes in Progress
1 comment:
TO CANCEl a P.O:-
There is no Tcode as such which delete PO .We can delete the line of PO in transaction ME22N(item level) OR we can ARCHIVE it using ME98
You cannot delete PO.You can only delete item lines in PO.
There are 2 ways of doing it.
1. Go to transaction ME22N - select each item line & then delete.
2. On Item details, delivery tab there is indicator for Delivery complete.
Just, set the indicator & PO will be completed.
P.S:-It is a general practice to set delivery completed indicator rather than deleting line items.