Sunday, December 30, 2018

Factory Calender Setup


1.Go to SCAL transaction

2.There will be three options.


    Click first public holidays and go in change mode.

    Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)

3.Now click Holiday calendar and go in change mode.

Click create and give holiday Cal id and description.

Click assign public holiday and add your holidays one by one and save

Now holiday cal is created.

4.Now come out and choose fact calendar and go in change mode

Click create and give Factory calendar id and description, and validity period.

Give the holiday calendar ID.

If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define)

and save.

5.You have to assign factory calendar to PLANT

Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOGISTIC GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT

Choose your plant and go to details-You have to define factory calendar there