Based on the standard SAP example (PR>Quantities/Dates tab>Release data (Press F1),
Processing time Planned del. GR processing
Purchasing time time
|----------|---------------------|--------|
Release PO Delivery Date
date date date required
Date required : 01.10.2007
GR processing time : 2 days (working days)
Planned delivery time : 10 days (calendar days)
Purchasing dept processing time : 2 days (working days)
For the material to be available on the date it is needed, the purchase
requisition must be released on 13.09.2007 (requirement date less GR processing
time, planned delivery time, and purchasing department processing time).