Approval process of expenditure is termed as Release Procedure in SAP.
or
The release process for the procurement of material & services, rather than relying for manual signatures.
We can define Release procedure in two ways.
1. with Classification
Used for Header level and Item Level releases.
PR, PO are release both Header level and Item Level.
2. without Classification
Used for Item Level releases.
PR only can release Item Level.
CLASSIFICATION:
Classes allow you to classify materials with the same characteristics. Classification data allows you to search for materials on the basis of the characteristic values entered into the classes. A material can be assigned to one or more classes. Classification data is valid for the whole company.
This feature is very useful when the customer wants to search for a particular vendor and particular batches.
Eg: Maruthi is manufacturing cars.
Note: we can use multiple parameters for classification
Some areas where classification is used:
Material Classification 001 Equipment Classification 002
Batch Classification 023 Release Procedure 032
Variant Configuration 300
Release Procedure {Plant, value} ---Multiple parameters
Terminologies for Release Procedure
1. Release Conditions: -
Identifies the release strategy
For e.g.
• If the price ranges from 1 to 1000, It is approved by AA, BB, and CC
• If the ranges from1001 to 1Lac then it is approved by AA, BB, CC, and DD
Identifies the release strategy
For e.g.
• If the price ranges from 1 to 1000, It is approved by AA, BB, and CC
• If the ranges from1001 to 1Lac then it is approved by AA, BB, CC, and DD
2.Release Strategy
Process of approving the document in a sequence is called as Release Strategy. Guides how to release the document. Guides who has to release the document.
It is a unique set of conditions, sequence and level of release.
It is a 2 digit code e.g. S1, S2, S3etc.
The Release Strategy contains the following: -
• Release Group
• Release Codes
• Release Indicators
It is a 2 digit code e.g. S1, S2, S3etc.
The Release Strategy contains the following: -
• Release Group
• Release Codes
• Release Indicators
• Release Prerequisite
Maximum release codes in a strategy are eight.
3.Release Group:-
It is a 2-digit code, grouping of approving authorities for the purpose of releasing the document. There could be any no. of releasing authorities in a group.
3.Release Group:-
It is a 2-digit code, grouping of approving authorities for the purpose of releasing the document. There could be any no. of releasing authorities in a group.
4. Release Codes: -
It is a 2digit code, which identifies the department or responsible person for
the approval process & release process.
E.g. AA - Manager
BB - Sr. Manager
CC - Vice President
DD - Managing Director
It is a 2digit code, which identifies the department or responsible person for
the approval process & release process.
E.g. AA - Manager
BB - Sr. Manager
CC - Vice President
DD - Managing Director
5.Release Indicator: -
It is a Code that represents the release status. If the proper approval
process is performed that the release Strategy has to be release if it is not
performed than the Release Strategy is blocked
R – Release
B – Blocked
It is a Code that represents the release status. If the proper approval
process is performed that the release Strategy has to be release if it is not
performed than the Release Strategy is blocked
R – Release
B – Blocked
6.Release Prerequisite
It will informs the system which RS has to be take place in the PO CEKKO is
a communication structure where it displays the field names & field lengths to
create characteristics i.e. we maintain characteristics in customizing by selecting
the field names from this communication structure for all external documents.
CEBAN is used for the purchasing requisition.
It will informs the system which RS has to be take place in the PO CEKKO is
a communication structure where it displays the field names & field lengths to
create characteristics i.e. we maintain characteristics in customizing by selecting
the field names from this communication structure for all external documents.
CEBAN is used for the purchasing requisition.
7. Alternate Release
Parallel authorities